How many cubes per pour — and where a 7-day reading comes from. A sample is three specimens at 28 days (IS 456 Cl 15.3); a 7-day result needs a separate sample.

Sampling Planner Calculator

Why this calc exists

Sampling is the boring-but-critical first link in the acceptance chain. Too few cubes and a bad pour gets through; too many and the lab is overwhelmed. IS 456 Cl 15.2.2 gives a frequency band that depends on the volume placed, and Cl 15.3 fixes a sample at three specimens tested at 28 days. Neither tells you exactly how many samples YOUR pour needs.

The rules: IS 456 Cl 15.2.2 sets bands of volume placed — 1 sample for 1–5 m³, 2 for 6–15 m³, 3 for 16–30 m³, 4 for 31–50 m³, and above 50 m³ four plus one more for every further 50 m³, with at least one sample per shift. A sample is 3 specimens, all at 28 days. For grades M30+, the designer may specify tighter sampling (some consultants double the frequency). The Sampling Planner calculator takes the pour volume, grade, and acceptance regime, and returns the cube count + sampling schedule.

Code references (with provenance)

  • IS 456 Cl 15.2.2 — Sampling frequency by volume placed: 1 sample for 1–5 m³, 2 for 6–15 m³, 3 for 16–30 m³, 4 for 31–50 m³; above 50 m³, 4 samples plus one more for every further 50 m³ or part of it, and at least one sample from each shift.
  • IS 456 Cl 15.3 — Sample size: three test specimens for each sample, all tested at 28 days. A 7-day or other-age reading comes from an additional sample (Cl 15.1.1).
  • IS 456 Table 8 — Assumed standard deviation, used where the plant has no established value.
  • IS 456 Table 11 — Conformity criteria the samples feed into.
  • IS 456 Cl 16.1 — Strength acceptance criteria.

Worked: 60 m³ M25 pour

Cl 15.2.2 sampling rate: 60 m³ is above 50 m³, so 4 samples plus one more for the further 10 m³ = 5 samples.

Cubes per sample: 3 specimens × 5 samples = 15 cubes for this pour, all tested at 28 days.

Lab workload: 15 cubes cast and broken at 28 days. A 7-day reading needs its own sample (Cl 15.1.1) — the three specimens in this sample are all 28-day.

Cost: cube casting ~₹50 each (mould, casting, breaking) → ~₹750 for this pour.

For an 8 m³ M25 pour: the 6–15 m³ band gives 2 samples → 6 cubes.

Field notes (what trips people up)

  • M30+ often tightens the rate. Some specifications (especially for infrastructure projects) set a frequency higher than the Cl 15.2.2 bands for M30 and above. Check the project spec.
  • One sample ≠ one cube. A sample is three specimens, all tested at 28 days (Cl 15.3). A 7-day reading comes from an additional sample, not from splitting the 28-day set.
  • Site lab capacity. Fifteen cubes is a half-day of casting and a day of breaking. Plan lab capacity against the pour schedule, and remember that a 7-day set is a second casting.
  • Small pours are not exempt. Even a 3 m³ pour needs at least 1 sample = 3 cubes. The cube cost is a tiny fraction of the pour cost — don't skip.

Worked example

Site: 1,200 m³ podium slab pour, M40 grade.

Project spec: 2 samples per 50 m³ — tighter than the Cl 15.2.2 bands for M40.

Samples: 1,200 / 50 × 2 = 48 samples.

Cubes: 48 × 3 = 144 cubes, all broken at 28 days. Lab capacity: 9 cubes per testing day → 16 days of breaking to book across the pour.

Field-checklist blocks

A short questionnaire, an inspector's checklist, and three worked examples that show how a sampling plan is set by the pour volume, the project specification and the lab's diary.

Questionnaire — ask before the pour is scheduled

  1. What is the pour volume, since the sampling rate steps at 5, 15, 30 and 50 m³?
  2. Is the project specification tighter than IS 456 Cl 15.2.2 — some specs raise the rate for M30 and above, and the project spec governs?
  3. For a pour above 50 m³, has the sample count been read off the Cl 15.2.2 band table, four samples plus one more for every further 50 m³ or part of it?
  4. Is the cube count planned as three per sample, all broken at 28 days, with any 7-day reading cast as a separate sample?
  5. Has the lab been booked for the casting day and for the 28-day breaking days?
  6. Does the schedule carry the 28-day acceptance set, or is only the 7-day leading indicator planned?
  7. For a small pour, is a sample still being taken? Even a 3 m³ pour needs at least one sample of three cubes.

Inspector's checklist — what to verify before and on the pour

  1. Sampling rate read off Cl 15.2.2 for the actual pour volume, with the band written on the pour card.
  2. Sample count at least 1 per pour, applied after the volume calculation and not before it.
  3. Cube count = samples × 3, all broken at 28 days.
  4. Sample locations marked on the pour card, with the cubes taken from the batch as placed rather than from a convenient corner.
  5. Specimen refs unique per cast set, so two sets from one pour cannot merge into a single sample in the register.
  6. Lab capacity booked for casting and for the 28-day breaking, with the breaking days named.
  7. Cost booked against the pour, at roughly ₹50 a cube including mould, casting and breaking.

What happens if… three worked examples

Example 1 — 60 m³ M25 pour

What happens. 60 m³ is above 50 m³, so Cl 15.2.2 gives four samples plus one more for the further 10 m³ — five samples. At three specimens each, that is 15 cubes.
Likely outcome. 15 cubes cast and broken at 28 days, at about ₹50 a cube for mould, casting and breaking, so ₹750 for the pour. A 7-day reading needs its own sample, cast and broken separately. The lab time is a half-day of casting and a day of breaking.
Correction. None on the count. Plan the breaking days as well as the casting day, because the 28-day set is the contract acceptance.

Example 2 — an 8 m³ M25 pour

What happens. 8 m³ falls in the 6–15 m³ band, so Cl 15.2.2 gives two samples, so 6 cubes.
Likely outcome. A small pour draws a disproportionate amount of lab effort for its size, and that makes skipping the sample tempting. Even a 3 m³ pour needs at least one sample of three cubes.
Correction. Take the sample. The cube cost is a tiny fraction of the pour cost, and an un-sampled pour is the one nobody can prove anything about later.

Example 3 — 1,200 m³ podium slab, M40, spec at 2 samples per 50 m³

What happens. The project specification is tighter than the Cl 15.2.2 bands, giving 1,200 ÷ 50 × 2 = 48 samples, and 48 × 3 = 144 cubes.
Likely outcome. At nine cubes per testing day, the breaking stretches over sixteen days across the pour; a 7-day reading adds a second casting. The cube count and the lab booking have to move together, or the 28-day set slips behind the structure.
Correction. Read the project spec before the IS 456 default, book the lab against the higher count, and keep the sample locations marked on the pour card.

FAQ

Why three specimens per sample?

IS 456 Cl 15.3: three test specimens for each sample, cast and tested at 28 days. Averaging the three smooths out specimen-to-specimen variation from compaction and curing, so the recorded strength represents the batch rather than one cube. If the individual variation exceeds ±15% of the average, Cl 15.4 makes the sample result invalid.

What if I want to do only 7-day tests?

Not on the strength of the acceptance sample. The three specimens in a sample are all 28-day specimens (Cl 15.3), and a 7-day result comes from an additional sample (Cl 15.1.1). Cl 15.1 also makes the 28-day compressive strength the sole criterion for acceptance; 7-day is a leading indicator only. The cube cost is dominated by casting (~₹25), not testing (~₹25), so saving the 28-day set is false economy.

How does this fit with the acceptance criteria calc?

The sampling planner tells you HOW MANY cubes; the cube test statistics calc takes the cube results and checks against IS 456 Table 11. Use them sequentially: plan → cast → break → evaluate.

Related reading & tools

AH
About the author

Amit Haridas

amit@concreteinfo.in

Indicative tool — not a substitute for engineering judgement. Results are computed from formulae and reference values cited to Indian Standards and other published codes as named on this page, using nominal default assumptions; clause and table references are given in good faith for study and preliminary checks. Always verify the current edition and amendments of any cited standard in the BIS catalogue before relying on it. Final mix proportions, structural checks and construction decisions must be confirmed by a qualified engineer against the project design brief, drawings and site conditions. ConcreteInfo accepts no liability for design, procurement or construction decisions taken on the basis of these tools. Code references & rights: Indian Standards are the property of the Bureau of Indian Standards (© BIS) — official PDFs at bis.gov.in. Shared in good faith as technical reference for the civil engineering fraternity — always verify against the official publication.
Newsletter

Technical updates, not sales emails

One email when a new article goes out on concrete technology, QA/QC and construction quality. No promotions, and your address is never sold or passed to advertising networks. Subscribing is separate from making an enquiry.

You are on the list.

One email when a new article goes out. Every issue carries an unsubscribe link.