Skip to main content

RMC Rate Calculator — IS 10262 BOM Cost + Plant Output Significance

Translating IS 10262 typical mix BOM into ₹/m³ — and the production-side math that tells you whether your plant is mixer-bound or truck-bound.

RMC Rate — transit mixer and plant conveyor with cost indicator

Why this calc exists

Two questions every RMC plant owner or contractor asks: 'what should I charge per m³?' and 'how many m³ per hour can my plant produce?' The first is a BOM cost arithmetic; the second is a production-rate accounting. They look unrelated but both drive the bottom line — charge too little and you lose money; produce too few m³ and you miss delivery slots.

IS 10262:2019 Annex A gives informative worked examples of typical mix proportions per m³ for M20–M60 — cement, water, sand, CA, w/c. These are not mix-designs (a project-specific mix from a designer supersedes them) but they're a defensible template for cost estimation. The production-rate side is standard cycle-time × fleet-utilisation accounting. The RMC rate calculator handles both, with editable inputs for local unit costs.

Code references (with provenance)

  • IS 10262:2019 — Concrete mix proportioning guidelines. Annex A gives informative worked examples (M20–M60 typical mixes).
  • IS 456 Cl 9 — Mix design requirements (nominal mix M20 or below; design mix above).
  • IS 4926:2003 — Ready-mixed concrete — code of practice (delivery, sampling, transport time limits).
  • GST Schedule II — RMC treated as a composite supply, 18 % GST on delivered price (consult your CA for current rate and ITC treatment).

Worked: M30, Pune, 25 km delivery, 30 % fly ash

BOM: cement 280 kg, fly ash 120 kg, water 160 L, sand 650 kg, CA 1240 kg, admixture 4 kg (1 %).

Material cost (₹/kg): 280×7 + 120×2.5 + 650×1.2 + 1240×1.4 + 4×120 + 160×0.05 = 1960 + 300 + 780 + 1736 + 480 + 8 = ₹5,264/m³ subtotal.

Freight: 25 km × ₹4/km/m³ = ₹100.

Wastage × Profit: ₹5,264 × 1.05 × 1.10 = ₹6,080. + ₹100 = ₹6,180 ex-plant.

GST 18 %: ₹6,180 × 1.18 = ₹7,292 / m³ delivered.

Plant (Tab B): 1 m³ mixer, 90 s cycle, 6 trucks × 10-min round trip → mixer 40 batches/hr vs trucks 36/hr → truck-bound at 36 m³/hr.

Field notes (what trips people up)

  • IS 10262 Annex A is informative. The figures are median crushed-aggregate mixes — MSA 20 mm, 75–100 mm slump, no admixture unless noted. For a specific project, the designer-of-record's mix design supersedes these.
  • Fly ash is cheaper than cement but slower strength gain. The cost saving is real; the schedule impact (longer formwork striking time, later prestress release) is the trade-off. IS 456 Cl 5.2 governs mineral admixtures.
  • GST on RMC is composite. 18 % on the all-in delivered price (Schedule II entry for RMC). Cement input credit (ITC) is generally not available since RMC is the composite supply, but consult your CA for current rules.
  • Mixer-vs-truck bottleneck. The Tab B output tells you which is the limit. Truck-bound → add trucks (cheap). Mixer-bound → need a second mixer or shorter cycle (expensive).

Worked example

Site: small RMC plant in Pune, 1 m³ mixer, 90 s cycle, 6 trucks.

Max output: 36 m³/hr, 288 m³/shift, 7,200 m³/month.

Avg price: ₹7,000/m³ delivered.

Monthly revenue: 7,200 × 7,000 = ₹5.04 cr.

Variable cost: ~₹5,500/m³ (material + freight). Margin: ₹1,500/m³ ≈ 21 %.

Field-checklist blocks

A short questionnaire, an inspector's checklist, and three worked examples that show how a delivered rate and a plant's real output are decided by the same handful of inputs.

Questionnaire — ask before the rate is quoted or the plant is planned

  1. Is the mix a project-specific design mix or the Annex A template? If it is the designer-of-record's mix, has that been used for the BOM rather than the typical proportions?
  2. Are the material prices current and local — cement, fly ash, sand, CA, admixture and water, all in ₹/kg?
  3. Is the delivery distance priced on the real route, since 25 km × ₹4/km/m³ is the freight line and it moves with every kilometre?
  4. Has the GST treatment been confirmed with the CA — 18 % on the delivered price, and the cement ITC question, because RMC is a composite supply?
  5. Is the plant mixer-bound or truck-bound, and does the output figure come from the lower of the two?
  6. Is the fleet sized for the delivery radius — the rule of thumb is 5–8 trucks per plant for a 25–30 km radius?
  7. If fly ash is in the mix, has the schedule effect been priced in — longer formwork striking time and later prestress release under IS 456 Cl 5.2?

Inspector's checklist — what to verify in the rate build-up

  1. BOM built per m³ from the actual mix, with each material's unit rate written against it.
  2. Wastage and profit factors stated separately — 1.05 and 1.10 in the worked case — so the delivered price can be defended line by line.
  3. Freight calculated on the real route distance, not on the straight-line radius.
  4. GST applied on the all-in delivered price at the composite-supply rate, with the CA's confirmation on record.
  5. Bottleneck identified — mixer capacity against truck capacity — and the output figure taken from the lower.
  6. Fleet checked against the delivery radius before another truck is bought.
  7. Achieved selling price compared with the built-up rate, since the gap between the ex-plant figure and the delivered price is where the margin lives.

What happens if… three worked examples

Example 1 — M30 in Pune, 25 km delivery, 30 % fly ash

What happens. The BOM is 280 kg cement, 120 kg fly ash, 160 L water, 650 kg sand, 1,240 kg CA and 4 kg admixture, which at local rates comes to ₹5,264 per m³. Freight adds ₹100 at ₹4/km/m³ over 25 km. Wastage × 1.05 and profit × 1.10 give ₹6,080 plus freight, so ₹6,180 ex-plant, and 18 % GST takes it to ₹7,292 delivered.
Likely outcome. The rate is defensible line by line, and every input can be re-derived by anyone who checks it.
Correction. None on the arithmetic. Re-price as soon as a cement or fly ash rate moves, because this figure has four moving parts before freight even enters.

Example 2 — the plant turns out to be truck-bound

What happens. With a 1 m³ mixer on a 90 s cycle the mixer can produce 40 batches an hour, but six trucks on a 10-minute round trip can only absorb 36.
Likely outcome. The plant runs at 36 m³/hr, not 40. The constraint is not production capacity, it is the fleet standing on the road.
Correction. Add trucks — that is the cheap fix, and the output tab tells you it is the right one. A second mixer is the expensive answer to a problem this plant does not have.

Example 3 — a delivered rate quoted below the built-up cost

What happens. The plant quotes ₹7,000 per m³ delivered against a built-up ₹6,180 ex-plant plus 18 % GST, while the variable cost sits around ₹5,500 per m³ including material and freight.
Likely outcome. The ₹1,500 per m³ margin looks comfortable at 21 %, but a rate quoted below the GST-inclusive ₹7,292 leaves the plant working for its overheads. On 7,200 m³ a month the gap does not stay theoretical.
Correction. Rebuild the rate from the BOM before quoting, and keep ex-plant, freight, GST and margin as separate lines so a buyer who pushes on price pushes on one line at a time.

FAQ

Why IS 10262 Annex A and not Table 9?

Table 9 is for nominal mix (M5–M20) only. For design mix (M25 and above), IS 10262 governs. Annex A gives typical mix proportions per m³ for cost estimation.

Can I claim ITC on cement?

Generally no, because RMC is a composite supply under GST — the input cement is part of the output composite supply. Consult your CA for current treatment.

What's the typical fleet size for a 1 m³ mixer plant?

Rule of thumb: 5–8 trucks per plant for 25–30 km delivery radius. The bottleneck analysis confirms when more trucks are needed (truck-bound) vs when a second mixer is needed (mixer-bound).

Related reading & tools

  • ../calculators/rmc-rate.html — RMC Rate calculator
  • calc-trial-mix-batch-significance.html — Trial Mix Batch Significance
  • mix-design-masterclass-is10262.html — Mix Design Masterclass — IS 10262
AH
About the author

Amit Haridas

amit@concreteinfo.in

Indicative tool — not a substitute for engineering judgement. Results are computed from formulae and reference values cited to Indian Standards and other published codes as named on this page, using nominal default assumptions; clause and table references are given in good faith for study and preliminary checks. Always verify the current edition and amendments of any cited standard in the BIS catalogue before relying on it. Final mix proportions, structural checks and construction decisions must be confirmed by a qualified engineer against the project design brief, drawings and site conditions. ConcreteInfo accepts no liability for design, procurement or construction decisions taken on the basis of these tools. Code references & rights: Indian Standards are the property of the Bureau of Indian Standards (© BIS) — official PDFs at bis.gov.in. Shared in good faith as technical reference for the civil engineering fraternity — always verify against the official publication.
Newsletter

Technical updates, not sales emails

One email when a new article goes out on concrete technology, QA/QC and construction quality. No promotions, and your address is never sold or passed to advertising networks. Subscribing is separate from making an enquiry.

You are on the list.

One email when a new article goes out. Every issue carries an unsubscribe link.