Why this calc exists
The d²/162 formula for rebar weight per metre is one of the few formulas in concrete practice that every site engineer remembers. It comes from m = ρ × π × d² / 4 = 7850 × π / 4 / 1000 = 6.162 ≈ 1/162 kg/m for a bar of diameter d in mm. The 162 is just a convenient denominator; the actual constant is 162.2.
Why it matters: rebar procurement is by mass, but BBS quantities are by length. Without a fast d²/162 calculation, you can't reconcile the two, and you'll either over-order (cost) or under-order (halting pours). The rebar weight calculator does the calc in both directions: given length, output mass; given mass, output length.
Code references (with provenance)
- IS 1786:2008 — High strength deformed steel bars and wires for concrete reinforcement. Specifies nominal mass per metre for each bar size.
- IS 2502:1963 — Bending and fixing of bars.
- IS 456 Cl 26.2 — Reinforcement (bond, development, laps); material standards per IS 1786.
d²/162 reference table
Ø 6 mm: 6²/162 = 0.222 kg/m
Ø 8 mm: 0.395 kg/m
Ø 12 mm: 0.888 kg/m
Ø 16 mm: 1.578 kg/m
Ø 20 mm: 2.466 kg/m
Ø 25 mm: 3.854 kg/m
Worked: 2,500 running metres of Ø16 mm = 2,500 × 1.578 = 3,945 kg = 3.95 tonnes.
Field notes (what trips people up)
- Order by mass, never by bar count. A 12 m Ø16 bar weighs 18.94 kg nominal; actual could be 18.6–19.2 kg depending on the manufacturer's tolerance (IS 1786 allows ±7 % on individual bars, ±5 % on a sample of 10+). For bulk procurement, use 1.578 kg/m × total length + 3 % margin.
- d²/162 is nominal. IS 1786 nominal density is 7850 kg/m³; some manufacturers are slightly over (7900–8000) for better bond. Don't be surprised if your actual mass is 1–2 % above the d²/162 number.
- Coated rebar (epoxy, galvanised) weighs 2–5 % more. The base bar weight stays d²/162; the coating adds a small mass. Check the supplier's TDS.
Worked example
Site: 5,000 m² podium slab, 80 kg/m³ typical reinforcement ratio.
Estimated steel: 5,000 × 0.25 (slab thickness) × 80 = 100 tonnes.
Total: ~97,123 running metres, ~10,000 individual bars (12 m stock).
Field-checklist blocks
A short questionnaire, an inspector's checklist, and three worked examples that show how a BBS length and a purchase order are reconciled against a mill certificate that never quite matches the textbook.
Questionnaire — ask before the order is placed
- Is the order placed by mass rather than by bar count, so the BBS lengths and the mill certificate can be reconciled against each other?
- Which nominal mass per metre is used for each diameter — 0.222, 0.395, 0.888, 1.578, 2.466 and 3.854 kg/m for 6, 8, 12, 16, 20 and 25 mm?
- Has the 3 % margin been added to the mass per metre multiplied by the total length, for bulk procurement?
- Is the stock length confirmed with the supplier — a 12 m Ø16 bar weighs 18.94 kg nominal, so bar count and tonnage are two views of the same order?
- Is the mill tolerance understood — IS 1786 allows ±7 % on an individual bar and ±5 % on a sample of 10 or more?
- For coated bar, has the supplier's TDS weight been used, since epoxy and galvanised coating adds 2–5 % on top of the base bar?
- Is the mill's own nominal density checked — some manufacturers run 7,900–8,000 kg/m³ for bond, which puts the delivered mass 1–2 % above d²/162?
Inspector's checklist — what to verify against the BBS and the delivery
- BBS running-metre total computed for each diameter before any tonnage is quoted.
- d²/162 applied per diameter, and the result cross-checked against the IS 1786 nominal mass for that size.
- Running metres and bar count both recorded against the 12 m stock length, so the two never drift apart.
- Mill certificate mass reconciled against the calculated mass for every delivery, with the variance written down.
- Coating weight added wherever the bar is coated, on the supplier's figure.
- Stock length confirmed before the bar count is fixed, since a change in stock length changes the number of joints and the offcut.
- Bundles handled by summing individual lengths in the BBS, with the equivalent diameter used only for the spacing check.
What happens if… three worked examples
What happens. At 1.578 kg/m the mass is 2,500 × 1.578 = 3,945 kg, or 3.95 tonnes.
Likely outcome. That is the figure that goes on the purchase order, and it reconciles with the mill certificate to within the IS 1786 tolerance.
Correction. None. Keep the d²/162 figure and the certificate figure side by side, so a 1–2 % variance from a mill running 7,900–8,000 kg/m³ does not read as a shortage.
What happens. The order goes out as a number of 12 m bars, and the tonnage is worked out afterwards from the mill's invoice rather than from the BBS.
Likely outcome. A 12 m Ø16 bar is nominally 18.94 kg but can sit anywhere in 18.6–19.2 kg on the manufacturer's tolerance, and the delivered mass can run 1–2 % above d²/162. The invoice then disagrees with the BBS by a margin nobody can explain.
Correction. Order by mass from the BBS with the 3 % margin for bulk procurement, and reconcile against the certificate at the delivery rather than at the invoice.
What happens. The estimate is 5,000 × 0.25 × 80 = 100 tonnes, which is about 97,123 running metres, or roughly 10,000 individual bars at 12 m stock.
Likely outcome. The estimate is the number the commercial team carries. It reconciles to the BBS only if the BBS lengths are checked bar by bar, and a rate-based steel estimate is not a schedule.
Correction. Run the BBS lengths through d²/162 for each diameter and reconcile the two totals before the tonnage is committed.
FAQ
Why exactly 162?
From m = ρ × A × L = 7850 × π × (d/2)² / 1000 = π × 7850 / 4000 × d² = 6.162 × d² ≈ d²/0.162. The 162 is 1000/(π·7850/4) — a convenient denominator. The more precise constant is 162.2.
Is the calculator accurate for Fe415 vs Fe500?
Yes — d²/162 is purely geometric (depends on density, not yield strength). Fe415, Fe500, Fe550 all use the same nominal mass.
What about bundled bars?
Two bars in contact: equivalent single bar = d × √2. Three bars: d × √3. For BBS, just sum individual lengths (the bundle is a delivery convention, not a structural change in the steel area).
Related reading & tools
- ../calculators/rebar-weight.html — Rebar Weight calculator
- calc-bbs-cutting-length-significance.html — BBS / Cutting Length Significance
- reinforcement-steel-is1786.html — Reinforcement Steel — IS 1786 (blog)
Technical updates, not sales emails
One email when a new article goes out on concrete technology, QA/QC and construction quality. No promotions, and your address is never sold or passed to advertising networks. Subscribing is separate from making an enquiry.