Skip to main content

Crack Injection Quantity Calculator — Epoxy/PU Resin Significance

Estimating epoxy or PU resin, packers, and surface-seal putty for structural and non-structural crack injection — including the wastage that site practice usually underestimates.

Crack Injection Quantity Calculator

Why this calc exists

Crack injection is small in volume but expensive per kg — epoxy resin runs ₹1,200–2,500/kg. Under-estimate the resin and you're 30 % over budget; over-estimate and you're returning opened bottles that have cured in the can. The dimensions are deceptively simple (length × width × depth) but the actual crack depth in a concrete element is rarely what you measure on the surface.

For structural cracks (active, structural, water-retaining structures), epoxy resin is the default — high tensile strength, bonds to dry concrete, fills voids as small as 0.1 mm. For moving or wet cracks (expansion joints, water tanks, basements), polyurethane is preferred because it remains flexible. The Crack Injection Quantity calculator takes crack dimensions, resin type, and packer spacing — outputs resin in kg, packers in number, and surface-seal putty in kg.

Code references (with provenance)

  • Repair practice (EN 1504 principles) — Repair materials must be at least as durable as the parent concrete.
  • IS 516 (Part 5/Sec 1):2018 — UPV for crack depth measurement (BS 1881-203 transit-time method).
  • ACI 224.1R — Causes, evaluation, and repair of cracks in concrete (international).
  • Product TDS — resin viscosity, working time, mixing ratio, bond strength.

Worked: 12 m of 1 mm-wide structural crack, 150 mm deep, epoxy injection

Crack volume: 12 × 0.001 × 0.150 = 0.0018 m³ = 1.8 L wet resin.

Resin density: 1,100 kg/m³ (typical low-viscosity epoxy). Mass = 1.8 × 1.1 = 1.98 kg.

Wastage: 25 % (over-pumping, surface spill, pot loss) → 2.5 kg resin.

Packers: spacing 200 mm (typical for 150 mm depth), 12 m / 0.2 = 60 ports × 1.3 (corner/end extra) = 78 packers.

Surface-seal putty: 5 mm thick × 50 mm wide along 12 m = 0.003 m³ = ~4.5 kg.

Total cost (epoxy at ₹2,000/kg): 2.5 × 2,000 + 78 × ₹35 + 4.5 × ₹150 = ₹5,000 + ₹2,730 + ₹675 = ₹8,405.

Field notes (what trips people up)

  • Crack depth is what surprises you. Surface 1 mm cracks often go 80–150 mm deep in a slab; in a beam, they may run full depth. Measure with UPV transit-time method or a scope camera before bidding.
  • Wider ≠ more resin. Most crack widths are 0.3–3 mm; doubling width doubles resin volume but adds little engineering benefit (you've already lost structural continuity past the resin bond strength).
  • Packer spacing depends on depth. Rule of thumb: spacing ≤ 1.5 × depth. For 100 mm crack: packers every 150 mm.
  • Pressure is the limiting factor. Too low and the resin doesn't reach the crack tip; too high and the concrete blows out. Start at 1 bar, ramp to 4–7 bar for epoxy.

Worked example

Site: 25 m of hairline cracks in a basement wall, 0.5 mm wide, 200 mm deep, water seepage.

Output: 2.5 L wet resin · 4.2 kg PU (water-reactive) · 150 packers · 8 kg putty · cost ≈ ₹18,000.

Note: PU resin volume calculation includes the chemical reaction expansion (~3×); adjust based on TDS.

Field-checklist blocks

A short questionnaire, an inspector's checklist, and three worked examples that show how a depth guess and a resin choice turn into an injection that does not fill the crack.

Questionnaire — ask before the injection is priced

  1. Is the crack structural, dry and static (epoxy) or moving and wet (PU)? The choice changes the resin, the volume and the price.
  2. How was the crack depth established — UPV transit-time per IS 516 (Part 5/Sec 1):2018, or a core? A surface 1 mm crack often runs 80–150 mm deep in a slab, and full depth in a beam.
  3. What wastage allowance is in the estimate — 25 % for over-pumping, surface spill and pot loss on epoxy?
  4. Is the packer spacing tied to the depth — the rule of thumb is spacing no more than 1.5 × depth, so every 150 mm for a 100 mm crack?
  5. Have the injection pressure limits been set — start at 1 bar and ramp to 4–7 bar for epoxy?
  6. For a PU crack, is the expansion factor from the TDS carried into the volume — about 3×?
  7. Has the face been confirmed dry and not actively leaking at the crack, since epoxy bonds to dry concrete and will not bond to a wet face?

Inspector's checklist — what to verify on the injection day

  1. Crack map recorded with width and length for every crack, on a scaled sketch of the element.
  2. Depth measured and documented, by UPV at three points along the crack or by core, before any resin is opened.
  3. Resin type confirmed against the crack behaviour, with the TDS viscosity, working time and mixing ratio on file.
  4. Resin quantity reconciled against the 25 % wastage and against what is actually consumed on the day.
  5. Packers installed at the calculated spacing, with the extra packers at the corners and ends.
  6. Surface seal laid and cured before injection — the 5 mm putty band along the crack.
  7. Injection log kept: pressure, time, resin consumed per packer, and the point at which resin appeared at the next packer or at the surface.

What happens if… three worked examples

Example 1 — 12 m of 1 mm structural crack, depth taken from the surface

What happens. The crack is priced at the width you can see and a guessed depth, when the actual depth in the element is 80–150 mm. Volume and packer count both come out of that guess.
Likely outcome. Resin is under-ordered and, more seriously, packers are spaced too far apart to reach the crack tip. The resin stops short, the crack is only partly filled, and the epoxy bond across the crack plane is never made.
Correction. Measure the depth by UPV transit-time per IS 516 (Part 5/Sec 1):2018 and set the packer spacing at 200 mm for a 150 mm depth, with the extra packers at corners and ends.

Example 2 — 25 m of 0.5 mm hairline cracks in a leaking basement wall

What happens. The wall is wet and seeping, so this is a moving, wet crack and PU is the right resin. PU also expands by about 3× in the reaction, and that factor has to be in the volume or the crack is under-filled.
Likely outcome. Priced on the epoxy figures (2.5 L wet resin, 78 packers) the job is under-scoped against the PU case (4.2 kg PU, 150 packers, 8 kg putty, about ₹18,000), and the injected PU is starved because nobody carried the expansion into the quantity.
Correction. Match the resin to the behaviour, apply the TDS expansion factor to the volume, and re-price the packer count at the depth-appropriate spacing.

Example 3 — injection pressure held at one setting from the first packer

What happens. The pump is set once and held there for the whole run instead of being ramped against what the crack is doing.
Likely outcome. Too low and the resin never reaches the crack tip, so the repair is a partial fill. Too high and the concrete blows out at the face, and you are back to the same crack with a new surface to treat. Either way the log shows a single pressure value for the whole job.
Correction. Start at 1 bar and ramp to 4–7 bar for epoxy, watching for resin to appear at the next packer, and record the pressure and the time at each packer.

FAQ

Epoxy or PU?

Epoxy for structural, dry cracks (high strength, brittle). PU for moving, wet cracks (flexible, water-reactive, expands 2–3×). Match resin to the crack behaviour.

How do I measure crack depth?

Non-destructive: UPV transit-time method per IS 516 (Part 5/Sec 1):2018 (BS 1881-203). Destructive: core through the crack and inspect. For most projects, UPV at three points along the crack gives a defensible average.

Can injected cracks be load-bearing again?

Epoxy-injected cracks typically restore 70–90 % of the original tensile capacity across the crack plane. Not a structural 'repair' in the strength-restoration sense, but adequate for water-tightness and most service conditions.

Related reading & tools

AH
About the author

Amit Haridas

amit@concreteinfo.in

Indicative tool — not a substitute for engineering judgement. Results are computed from formulae and reference values cited to Indian Standards and other published codes as named on this page, using nominal default assumptions; clause and table references are given in good faith for study and preliminary checks. Always verify the current edition and amendments of any cited standard in the BIS catalogue before relying on it. Final mix proportions, structural checks and construction decisions must be confirmed by a qualified engineer against the project design brief, drawings and site conditions. ConcreteInfo accepts no liability for design, procurement or construction decisions taken on the basis of these tools. Code references & rights: Indian Standards are the property of the Bureau of Indian Standards (© BIS) — official PDFs at bis.gov.in. ACI references are copyrighted by the American Concrete Institute — official documents at concrete.org. BS/EN references are copyrighted by BSI and CEN — bsigroup.com. Shared in good faith as technical reference for the civil engineering fraternity — always verify against the official publication.
Newsletter

Technical updates, not sales emails

One email when a new article goes out on concrete technology, QA/QC and construction quality. No promotions, and your address is never sold or passed to advertising networks. Subscribing is separate from making an enquiry.

You are on the list.

One email when a new article goes out. Every issue carries an unsubscribe link.