Why this calc exists

Brickwork quantity is a per-m² to per-m³ conversion with two unknowns: brick size and mortar thickness. Get the size wrong and you over-order by 10–25 %. Get the mortar thickness wrong and the sand-and-cement estimate is off by the same.

Standard modular clay bricks are 200 × 100 × 100 mm with 10 mm mortar joints, giving 500 bricks per m³ of wall (with 1:6 mortar). Non-modular sizes (230 × 110 × 70, 230 × 110 × 110) change the count. AAC blocks run 600 × 200 × 200 mm etc., giving ~42 blocks per m³ — almost an order of magnitude fewer. The Brickwork Quantity calculator takes wall dimensions, brick type, and mortar ratio, and outputs both the brick count and the cement/sand volumes for the mortar.

Code references (with provenance)

  • IS 1905 — Code of practice for structural use of unreinforced masonry. Mortar grades, joint thickness, brick absorption limits.
  • IS 1077 — Common burnt clay building bricks — specifications (modular 200×100×100).
  • IS 12894 — Fly ash-lime bricks.
  • IS 2185 (Part 3) — Autoclaved cellular (AAC) concrete blocks.

Worked: 10 m³ of 230 mm modular brickwork in 1:6 mortar

Brick count: 1 m³ / (0.20 × 0.10 × 0.10) = 500 bricks. With 10 % wastage → 550 bricks/m³ including breakage.

Mortar volume: 1 − (500 × 0.002) = 1 − 1.0 = 0 m³ nominal. Real mortar volume (with 10 mm joints) is ~25–30 % of wall → 0.30 m³/m³ wet.

Dry mortar volume: 0.30 × 1.33 = 0.40 m³ dry.

1:6 ratio (cement:sand): total parts 7 → cement = 0.40/7 = 0.057 m³ → 0.057 × 1440 = 82 kg = 1.65 bags/m³. Sand = 6 × 0.057 = 0.343 m³ loose.

For 10 m³: 5,500 bricks, 16.5 bags cement, 3.4 m³ sand.

Field notes (what trips people up)

  • Modular vs non-modular confusion. Many 'standard' bricks in India are actually non-modular (230 × 110 × 70). Always measure a sample of 10 bricks before calculating.
  • Wastage 5–10 %. 5 % on a controlled site, up to 10 % for new masons or rough handling. AAC blocks are brittle and crack at corners — use 5–8 %.
  • Sand bulking at moisture. Damp sand occupies 15–20 % more volume. Order by weight, not loose volume, when possible.
  • Mortar grade vs exposure. IS 1905 mortar designations (H1, H2, M1, M2, L1, L2) are selected by exposure. Coastal / severe: M2 (1:1:6 cement-lime-sand) or richer; moderate: M1 (1:1:6); mild: L2 (1:2:9 or 1:3:12).

Worked example

Site: 240 m² of 230 mm brickwork in a Pune residential block.

Inputs: brick 230 × 110 × 75 mm, mortar 1:6, wastage 8 %.

Output: volume 55.2 m³ · bricks 6,800 · cement 91 bags · sand 19.6 m³ (order 22 m³ loose).

Field-checklist blocks

A short questionnaire, an inspector's checklist, and three worked examples that show how a brick-size assumption or a mortar-volume shortcut turns into a wall that costs more than the drawing allowed for.

Questionnaire — ask before the order is placed

  1. Have you measured a sample of 10 bricks and confirmed whether they are modular (200 × 100 × 100 mm) or non-modular (230 × 110 × 70 mm)?
  2. What wastage percentage is in the order — 5 % on a controlled site, up to 10 % for new masons or rough handling, 5–8 % for AAC blocks that crack at the corners?
  3. Does the mortar grade match the exposure under IS 1905 — H1 or H2, M1 or M2, L1 or L2 for the location the wall is going into?
  4. Is the mortar ratio the one the site will actually mix, and is the sand ordered by weight rather than loose volume, given the 15–20 % it bulks at moisture?
  5. Is the 10 mm joint thickness the one the mason is achieving, and has a test panel been laid?
  6. Are the wall dimensions taken on the face that will be plastered, with openings deducted on the same basis the quantity is measured?
  7. Has the delivered stack been reconciled against the ordered count — 5,500 bricks for 10 m³ — before the wall is plastered over?

Inspector's checklist — what to verify before the order goes out

  1. Sample of 10 bricks measured and recorded — length, breadth, height — and the modular or non-modular call written down.
  2. Wastage percentage stated on the order and applied to the count, rather than left to the mason's judgement in the yard.
  3. Mortar grade cross-checked against IS 1905 for the exposure condition of that wall, and the ratio on the order matches the grade selected.
  4. Mortar volume taken as the real figure — about 25–30 % of the wall, 0.30 m³ wet per m³, 0.40 m³ dry per m³ — and not from the nominal brick-volume arithmetic.
  5. Cement and sand split checked against the ratio: 0.057 m³ cement and 0.343 m³ sand loose per m³ at 1:6, which is 1.65 bags per m³ — 16.5 bags for 10 m³.
  6. Sand ordered by weight, with the 15–20 % bulking allowance applied to the loose figure on the day's stock.
  7. Delivered-stack reconciliation against the ordered count before the wall is closed up.

What happens if… three worked examples

Example 1 — the mortar volume taken from the nominal brick arithmetic

What happens. The brick volume is subtracted from the wall volume and the mortar comes out at 0 m³ nominal. The number looks absurd only because the nominal volume ignores the 10 mm joints entirely — and it is the number that gets carried into the order.
Likely outcome. Either no cement is ordered, or far too little of it. The mason mixes lean mortar on the spot to keep up with the masons, the joints are not 1:6, and the IS 1905 mortar grade for the exposure is not met.
Correction. Use the real mortar volume — 0.30 m³ wet per m³ of wall, 0.40 m³ dry — and split it at the stated ratio: 0.057 m³ cement and 0.343 m³ sand loose per m³.

Example 2 — a non-modular brick ordered on the modular 500-per-m³ rate

What happens. The quantity is taken off as 500 bricks per m³, but the brick on the stack is 230 × 110 × 70 mm. The two do not reconcile, and nobody measures until the delivery is already at the gate.
Likely outcome. The order covers the 10 m³ with stock to spare — 5,500 bricks for 10 m³ was the figure on the order, and the wall does not need them all. You have paid for and carted surplus brick and then stored it on a congested plot.
Correction. Measure 10 bricks before the order is placed and run the quantity on the size that is actually being delivered.

Example 3 — 3.4 m³ of sand ordered on the loose volume, in the monsoon

What happens. Sand is ordered to the loose-volume figure — 3.4 m³ for the 10 m³ of brickwork — but the sand in the yard is damp and occupies 15–20 % more volume.
Likely outcome. The mix runs short of sand, so it is stiff. The mason's response at the mixing tray is to add water, and the wall goes up with more water in the mortar than the 1:6 ratio on the drawing allowed.
Correction. Order sand by weight where you can. If you cannot, apply the 15–20 % bulking to the loose figure on the day's stock and order 3.4 m³ accordingly.

FAQ

How many bricks in 1 m³ of standard modular brickwork?

500 bricks nominally; 525–550 in practice with 5–10 % wastage.

Can I use this for AAC blocks?

Yes — the calculator supports AAC dimensions (e.g. 600 × 200 × 200 mm) and outputs blocks per m³ automatically.

What's the difference between cement mortar and cement-lime mortar?

Cement mortar (cement + sand) is stronger but less workable. Cement-lime mortar (cement + lime + sand) is more workable and less prone to cracking, used for plaster and masonry in seismic zones. IS 1905 Table 4 gives grades for both.

Related reading & tools

AH
About the author

Amit Haridas

amit@concreteinfo.in

Indicative tool — not a substitute for engineering judgement. Results are computed from formulae and reference values cited to Indian Standards and other published codes as named on this page, using nominal default assumptions; clause and table references are given in good faith for study and preliminary checks. Always verify the current edition and amendments of any cited standard in the BIS catalogue before relying on it. Final mix proportions, structural checks and construction decisions must be confirmed by a qualified engineer against the project design brief, drawings and site conditions. ConcreteInfo accepts no liability for design, procurement or construction decisions taken on the basis of these tools. Code references & rights: Indian Standards are the property of the Bureau of Indian Standards (© BIS) — official PDFs at bis.gov.in. Shared in good faith as technical reference for the civil engineering fraternity — always verify against the official publication.
Newsletter

Technical updates, not sales emails

One email when a new article goes out on concrete technology, QA/QC and construction quality. No promotions, and your address is never sold or passed to advertising networks. Subscribing is separate from making an enquiry.

You are on the list.

One email when a new article goes out. Every issue carries an unsubscribe link.